I-294, Chicago, Illinois



I-294-Case-Study-3Challenge

Various areas of a 42 mile stretch along I-294 had experienced settlement, leading to dips and bumps that posed safety challenges for drivers. The project had to be completed during the night, due to the high traffic volumes of the tollway and the inability to restrict the steady traffic flow. The project, due to its size, needed to be completed in five stages.

The Illinois State Toll Highway Authority released a bid letting for the raising of the tollway transition, approach, and sleeper slabs, using high density polyurethane foam. They required an experienced contractor solve the problem.

Project Summary

The bid letting specifications called for a 6 lb./cu.ft. foam with a minimum tensile and compression strength of 90 psi. RaiseRite exclusively uses HMI Foams (a world leader in concrete lifting equipment and materials), and HMI had a foam that easily met the requirements of the project.

The project called out a total of 100,650 pounds of material to be used. RaiseRite Concrete Lifting, Inc. of Manitowoc, Wisconsin was awarded the project after bid opening as a subcontractor through a large general contractor in Illinois. Since RaiseRite’s work was part of a larger rehabilitation project, there would need to be clearly stated communications and processes among all parties involved in the project.

The work was to be performed in stages. Five different areas needed to be raised along five lanes, approximately 100 feet on both sides of bridges, where the settlement had occurred. The specifications also called for a truck mounted pumping unit with certified flow meters able to measure the amount of foam injected. In order to inject the foam, RaiseRite needed to drill out 5/8” holes on a 4 foot grid pattern. Once the holes were drilled out, a zerk was inserted into each hole. The injection gun fastened to the end of the pumping hose was clamped to the zerk, allowing the polyurethane foam to be injected under the slab.

Solution

RaiseRite used a zip level and string line, approved by the Toll Highway Authority to monitor and measure elevation, ensuring an even plane on the roadway. RaiseRite successfully raised the areas required within the project scope, ensuring a smooth roadway service for travelers.

The project entailed RaiseRite drilling approximately 2,000 access holes and pumping a total of 84,744 pounds of HMI RR601 polyurethane foam to complete the job. The areas of roadway raised varied in amounts from as small as ½” to as much as 5”. Throughout the project, the Tollway engineer and a representative from the general contractor were always onsite to monitor the work, and verify lane closures were being followed for the safety of the crews and travelers.