Raise-Rite Foundation Pier System, Inc.

Methods of Foundation Repair
Company Profile
Foundation Piering Case Studies
Contact Us
Foundation Piering Case Studies
Raise-Rite Concrete Lifting, Inc.
Hydraulic Mudpumps, Inc.
Serving Wisconsin's foundation repair needs since 1994.

MENU:


FREEZER
Column supports heaved by frost

By Jeff Cvetezar

Foundation Piering Case Study: Foundation Heaved by Frost The Problem
The structure has experienced incresing amounts of heave throughout the floor due to below slab insulation failing to keep frost from reaching column footings.

Description of Structure
The freezer building is a steel frame structure with aluminum siding built on a 4 foot frost wall with a 12 x 24 x 12 footing.

Project Summary
Frost has advanced 10-12 feet below the original floor elevation under 80% of the area that has heaved. Ice lenses have formed within the frozen zone which is directly beneath the level that interior foundations bear.



Foundation heaved by frost
Resistance Piering Foundation Restoration Diagram Foundation Restoration
In each of 24 locations, 6' borings were drilled through an 18" concrete pad and 6-8' of frozen ground. Resistance piers were installed using quiet and vibration free hydraulic equipment. Each pier had a measured bearing capacity rating higher than the working load insuring that future settlement is unlikely. Once all piers were installed, the load was permanently transferred to the piers using hydraulic rams.


Success!
Each pier was installed and field load tested to a verified bearing stratum 46-1/2 feet below ground. The frozen soil was removed and the columns were lowered to their original position.

PROJECT STATISTICS
Installed By: RaiseRite Foundation Pier System Inc.
Number of Piers: 24 resistance
Part Number: PP/CLP3500.160M
Avg. Pier Depth: 43'-6"
Avg. Drive Force: 50,569 lbs
Avg Working Load: 22,500
Ultimate Capacity: 85,000
Factor of Safety: 2.22 (Drive to Lift)
(Averages) 3.70 (Ultimate to Lift)


^^^ Back to Top ^^^

TOWNHOUSE
Foundation settled

By Jeff Cvetezar

Foundation Piering Case Study: Settled Foundation Description of Structure
The project is located in Walker, MN on the shore of Leech Lake. The two unit building, constructed in 1996, is approximately 115' x 50' with a full basement and walk-out facing Leech Lake. The foundation for the structure consists of typical spread footings and masonry block walls. The upper stories are wood frame construction.

Notable Problems
  • Garage Floor settled in corner
  • Garage door opening wider at the bottom
  • Step cracking along mortor joints
  • Separation of window extensions
  • Differential movement between sheer-rock and fireplace
  • Separation of porch and foundation
  • Interior doors out of square



Project Summary
Based on observations, there is reason to believe that the building is situated above an abandoned railroad embankment. Borings indicate the fill soils placed in 1996 were likely added above existing fill soils placed above compressible swamp deposited materials.


Foundation Piering In Process for Settled Foundation
PROJECT STATISTICS
Installed By: RaiseRite Foundation Pier System Inc.
Number of Piers: 45 helical, 24 resistance
Part Number: AP2-3500.165, RD-2875.262, RD-3500.300
Avg. Pier Depth: 60 Feet
Avg. Drive Force: 70,000 lbs
Helical Foundation Piering Diagram



Success!
Tieback helical piers were used to stabilize resistance piers (as shown at right) so that the footing did not push inward when the basement floor was removed. Each pier was installed and field load tested to a verified bearing stratum 60' below grade. The structural load was transferred from unstable soil to the piers. Settlement was recovered and the structure was restored to the approximate original elevation.


^^^ Back to Top ^^^

RESIDENTIAL FOUNDATION REPAIR
Basement wall bowing in

By Jeff Cvetezar

Description of Structure
The structure is a one story home with a block foundation.

The Problem
The foundation wall was bowing in approximately 2" on the third course of block from the top. The affected area was 36' long.

Foundation Piering Case Study: Bowed Basement Wall The Solution
The fill from along the foundation was excavated. Five (5) helical tieback piers were installed every seven (7) feet to anchor the wall, and pull the wall straight. Once the wall was straightened, 3/4" stone was used to back fill, and 12' layer of topsoil was added.



Diagram of Helical Foundation Piering for Bowed Basement Wall

Success!
After each pier was systematically torqued in small increments, the wall was perpendicular and integrity was regained.

PROJECT STATISTICS
Installed By: RaiseRite Foundation Pier System Inc.
Number of Piers: 5 helical tieback
Part Number: AHS-SQ1250
Flight: 8"/10"


^^^ Back to Top ^^^

Methods of Foundation Repair | Company Profile
Foundation Piering Case Studies | Contact Us


Copyright ©2006 Raise-Rite Concrete Lifting